Developer/Owner:
University of Pittsburgh
Project Status:
Under Review
Development Category:
Business
May 2020 - Submitted to the DRP
- Construction of a 45,000 square foot 3-story Chilled Water Plant for Upper Campus Facilities
- Located on Centre Avenue/Robinson Street Extension
- Will require a new Electrical Substation
- Pitt anticipates construction to begin November 2020 and operations to begin December 2022
- DRP conducted an internal review on May 6th
- Pitt invited to present to DRP contingent on additional information requested
June 2020 - Presented to the DRP
- The University of Pittsburgh Presented to the DRP during the June 3rd meeting
- Received a Score of 60% D against the GHMP
- The University invited to discuss areas of improvement to better align with the GHMP
- The DRP was joined by the university at the June 23rd meeting to discuss bringing the project into alignment with the GHMP
- The University has been invited to return to the DRP once improvements are made to bring the project into alignment
February 2021 - Response to Requested Information
- The Development Team sent response & updated documentation to DRP's additional requests/concerns
March 2021 - Presented to the DRP
- The University of Pittsburgh returned to the DRP for a second formal presentation
- The Developer presented robust solutions to the concerns outlined by the DRP
- The Development Project passed the DRP review with a score of 80% - B
- The Developer will present to the community during the April Quarterly Community Meeting